Dept. of Trans. PROGRESS Serial No. Contract No. 08-326-13-07 04-2A7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 41% 43% 04-MRN-37-11.2/14.5 Federal Project: 04-SON-101-25.9/37.0 NONE 04-MRN-101-1.1/10.7 Progress payment No. 03 Payment period ending: 11-20-08 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 540,124.00 332,351.82 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 540,124.00 332,351.82 5. Mobilization 120,175.00 25,300.00 6. Total Work Completed 660,299.00 7. Deductions 8. a.Contract Retentions -29,779.63 -9,002.41 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 630,519.37 348,649.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 348,649.41