Dept. of Trans. PROGRESS Serial No. Contract No. 07-354-09-04 04-2A7604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 67% 04-SM-92-11.8/12.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-07 PENHALL COMPANY 13750 CATALINA STREET SAN LEANDRO CA 94577 Escrow No. 02314 Total Estimate This Estimate 1. Contract Itms Without Mobil. 963,127.64 348,961.68 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 963,127.64 348,961.68 5. Mobilization 47,526.00 0.00 6. Total Work Completed 1,010,653.64 7. Deductions 8. a.Contract Retentions -48,156.38 -17,448.08 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 962,497.26 331,513.60 10. Reduction Amt to Escrow 11. Payment to Escrow 48,150.00 12. Net Pymt. this Estimate 331,513.60