Dept. of Trans. PROGRESS Serial No. Contract No. 07-263-12-36 04-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 37% 04-SM-101-11.9/23.7 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-07 PENHALL COMPANY 13750 CATALINA STREET SAN LEANDRO CA 94577 Escrow No. 02313 Total Estimate This Estimate 1. Contract Itms Without Mobil. 782,016.88 253,028.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 782,016.88 253,028.50 5. Mobilization 135,000.00 6,750.00 6. Total Work Completed 917,016.88 7. Deductions 8. a.Contract Retentions -39,100.84 -12,651.42 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 877,916.04 247,127.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 247,127.08