Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-300-15-06 04-2A8004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SCL-9-6.7/ .0 Federal Project: 04-SCL-17-13.9/ .0 NONE 04-SCL-101-R0.8/ .0 Progress payment No. 08 Payment period ending: 10-19-12 MURPHY INDUSTRIAL COATINGS INC 2704 GUNDRY AVENUE SIGNAL HILL CA 90755 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,039,160.00 119,395.60 2.a. Extra Work 18,807.13 18,807.13 b. Adjustment Comp. 500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,058,467.13 138,202.73 5. Mobilization 50,000.00 0.00 6. Total Work Completed 1,108,467.13 7. Deductions -10,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,098,467.13 133,202.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 133,202.73