Dept. of Trans. PROGRESS Serial No. Contract No. 10-021-08-40 04-2A8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 100% 04-CC-80-0.8/1.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 01-20-10 TERNO INC 15701 HERON AVENUE LA MIRADA CA 90638 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 93,260.80 24,693.75 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 93,260.80 24,693.75 5. Mobilization 26,600.95 5,600.20 6. Total Work Completed 119,861.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -9,326.09 -2,469.38 c. Reduction after 95% Comp. 9. Total pay to Contractor 110,535.66 27,824.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,824.57