Dept. of Trans. PROGRESS Serial No. Contract No. 24-291-13-23 04-2A9704 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 100% Location: Federal Project: 04-SCL-280-11.6/18.8 IM 04-SM-280-6.7/R12.7 Progress payment No. 017 Payment period ending: 10-20-24 GHILOTTI CONSTRUCTION CO INC 246 GHILOTTI AVENUE SANTA ROSA CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,480,493.00 576,622.60 2. a. Extra Work 381,152.82 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 17,861,645.82 576,622.60 5. Mobilization 1,820,000.00 0.00 6. Total Work Completed 19,681,645.82 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,681,645.82 576,622.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 576,622.60