Dept. of Trans. FINAL Serial No. Contract No. 12-319-08-06 04-2E3704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SM-82-20.8/21.9 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-29-12 INTERSTATE GRADING AND PAVING INC 128 SO MAPLE AVE SO SAN FRANCISCO CA 94080 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 58,067.00 0.00 2.a. Extra Work b. Adjustment Comp. 410,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 468,067.00 0.00 5. Mobilization 6. Total Work Completed 468,067.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 468,067.00 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00