Dept. of Trans. PROGRESS Serial No. Contract No. 12-234-16-03 04-2E4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 36% 04-SCL-130-9.0/15.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 08-20-12 INTERMOUNTAIN SLURRY SEAL INC P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 123,610.48 123,610.48 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 123,610.48 123,610.48 5. Mobilization 6. Total Work Completed 123,610.48 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 123,610.48 123,610.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 123,610.48