Dept. of Trans. PROGRESS Serial No. Contract No. 12-264-14-16 04-2E6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 8% 04-NAP-121-9.4/22.1 Federal Project: ACST-P121(24) P Progress payment No. 01 Payment period ending: 09-20-12 GHILOTTI CONSTRUCTION COMPANY INC 246 GHILOTTI AVENUE SANTA ROSA, CA 95407 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 437,442.30 437,442.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 437,442.30 437,442.30 5. Mobilization 186,750.00 186,750.00 6. Total Work Completed 624,192.30 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 624,192.30 624,192.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 624,192.30