Dept. of Trans. PROGRESS Serial No. Contract No. 13-206-09-23 04-2E7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 46% 77% 04-ALA-580-30.6/30.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-20-13 BAY LINE CUTTING AND CORING INC 1635 4TH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 293,146.14 293,146.14 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 293,146.14 293,146.14 5. Mobilization 36,661.83 36,661.83 6. Total Work Completed 329,807.97 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 329,807.97 329,807.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 329,807.97