Dept. of Trans. PROGRESS Serial No. Contract No. 13-233-09-46 04-2E7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 98% 04-ALA-580-30.6/30.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-13 BAY LINE CUTTING AND CORING INC 1635 4TH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 518,014.14 224,868.00 2.a. Extra Work 67,398.97 67,398.97 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 585,413.11 292,266.97 5. Mobilization 38,591.40 1,929.57 6. Total Work Completed 624,004.51 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -29,226.70 -29,226.70 c. Reduction after 95% Comp. 9. Total pay to Contractor 594,777.81 264,969.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 264,969.84