Dept. of Trans. PROGRESS Serial No. Contract No. 12-024-08-38 04-2G2804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 100% 04-SOL-37-7.3 Federal Project: 04-SOL-37-7.3/7.3 NONE Progress payment No. 05 Payment period ending: 01-20-12 DISNEY CONSTRUCTION, INC 875 MAHLER ROAD, SUITE 188 BURLINGAME, CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 296,231.65 84,427.47 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 296,231.65 84,427.47 5. Mobilization 6. Total Work Completed 296,231.65 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 296,231.65 84,427.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,427.47