Dept. of Trans. PROGRESS Serial No. Contract No. 19-112-11-09 04-2G3504 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 84% Location: Federal Project: 04-SCL-280-18.2/18.6 HSIM-280-1(148) Progress payment No. 003 Payment period ending: 04-20-19 PELAGIC ENGINEERING 3600 HARBOR BLVD #85 OXNARD CA 93035 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 466,145.62 185,577.22 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 466,145.62 185,577.22 5. Mobilization 28,000.00 1,400.00 6. Total Work Completed 494,145.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 494,145.62 186,977.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 186,977.22