Dept. of Trans. PROGRESS Serial No. Contract No. 15-324-10-37 04-2G4104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 55% Location: Federal Project: 04-ALA-680-R19.9/R20.2 HSNH-PIG(680) 074-E Progress payment No. 002 Payment period ending: 11-20-15 FBD VANGUARD CONSTRUCTION 651 ENTERPRISE COURT LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 629,157.90 67,950.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 629,157.90 67,950.00 5. Mobilization 39,242.10 0.00 6. Total Work Completed 668,400.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 668,400.00 67,950.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,950.00