Dept. of Trans. PROGRESS Serial No. Contract No. 21-081-12-52 04-2G4604 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 31% Location: Federal Project: 04-ALA-13-10.9/12.0 ACNH-P013(37) Progress payment No. 002 Payment period ending: 03-20-21 CALIFORNIA HIGHWAY CONSTRUCTION GROUP INC 1647 WILLOW PASS RD #150 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 293,335.55 106,001.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 293,335.55 106,001.75 5. Mobilization 50,035.08 0.00 6. Total Work Completed 343,370.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 343,370.63 106,001.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 106,001.75