Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-200-10-10 04-2G6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-CC-24-5.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 05-28-12 BAY CITIES PAVING & GRADING 5029 FORNI DRIVE CONCORD, CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 761,552.88 136,039.36 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 761,552.88 136,039.36 5. Mobilization 6. Total Work Completed 761,552.88 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 761,552.88 136,039.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,039.36