Dept. of Trans. PROGRESS Serial No. Contract No. 12-170-10-11 04-2G6704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 14% 04-SM-92-R16.3/ .0 Federal Project: NONE Progress payment No. 01 Payment period ending: 06-20-12 SHIMMICK CONSTRUCTION COMPANY INC 8201 EDGEWATER DRIVE SUITE 20 OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 93,775.00 93,775.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 93,775.00 93,775.00 5. Mobilization 6. Total Work Completed 93,775.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 93,775.00 93,775.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 93,775.00