Dept. of Trans. PROGRESS Serial No. Contract No. 21-110-09-18 04-2G7304 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 90% Location: Federal Project: 04-SCL-85-18.0/24.1 ACNH-000C(506) 04-ALA-80-2.5/8.0 04-ALA-580-47.2/47.6 Progress payment No. 013 Payment period ending: 04-20-21 DREAMBUILDER CONSTRUCTION CORP 18543 YORBA LINDA BLVD #376 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,276,433.54 53,641.45 2. a. Extra Work 168,363.61 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,444,797.15 53,641.45 5. Mobilization 180,223.00 0.00 6. Total Work Completed 1,625,020.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,625,020.15 53,641.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,641.45