Dept. of Trans. PROGRESS Serial No. Contract No. 11-332-14-27 04-2G7904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 70% 36% 04-SM-35-3.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-11 PACIFIC ELECTRIC CONTRACTING 330 PHELAN AVENUE SAN JOSE, CA 95112 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,100.00 0.00 2.a. Extra Work 222,622.35 24,770.46 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 227,722.35 24,770.46 5. Mobilization 6. Total Work Completed 227,722.35 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 227,722.35 24,770.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,770.46