Dept. of Trans. PROGRESS Serial No. Contract No. 16-111-12-06 04-2G8304 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 38% Location: Federal Project: 04-ALA-13-8.8 STP-ER 19C1-004--(E) Progress payment No. 003 Payment period ending: 04-20-16 GRANITE CONSTRUCTION COMPANY 715 COMSTOCK ST SANTA CLARA CA 95054 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 404,998.31 264,223.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 95,858.00 -66,365.00 4. Earned Subject to Retention 500,856.31 197,858.10 5. Mobilization 114,000.00 0.00 6. Total Work Completed 518,998.31 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 614,856.31 197,858.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 197,858.10