Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-13-57 04-2G8904 PROGRESS PAYMENT VOUCHER %complete: %time: 82% 100% Location: Federal Project: 04-MRN-1-8.0/8.0 ACST-19D4(4) Progress payment No. 006 Payment period ending: 09-20-17 THOMPSON BUILDERS CORPORATION 250 BEL MARIN KEYS BLVD BLDG NOVATO CA 94949 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,886,496.50 69,953.95 2. a. Extra Work 151,751.45 20,982.69 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,038,247.95 90,936.64 5. Mobilization 100,000.00 0.00 6. Total Work Completed 2,138,247.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -9,093.66 -9,093.66 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,129,154.29 81,842.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,842.98