Dept. of Trans. PROGRESS Serial No. Contract No. 17-142-12-56 04-2G9904 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 11% Location: Federal Project: 04-SCL-130-5.6/6.0 ACST-PP13-0(4) Progress payment No. 001 Payment period ending: 05-20-17 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 132,945.04 132,945.04 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 72,679.96 72,679.96 4. Earned Subject to Retention 205,625.00 205,625.00 5. Mobilization 95,000.00 95,000.00 6. Total Work Completed 227,945.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 300,625.00 300,625.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 300,625.00