Dept. of Trans. PROGRESS Serial No. Contract No. 17-170-15-52 04-2G9904 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 26% Location: Federal Project: 04-SCL-130-5.6/6.0 ACST-PP13-0(4) Progress payment No. 002 Payment period ending: 06-20-17 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 453,658.89 320,713.85 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 17,558.92 -55,121.04 4. Earned Subject to Retention 471,217.81 265,592.81 5. Mobilization 95,000.00 0.00 6. Total Work Completed 548,658.89 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 566,217.81 265,592.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 265,592.81