Dept. of Trans. PROGRESS Serial No. Contract No. 17-233-14-54 04-2G9904 PROGRESS PAYMENT VOUCHER %complete: %time: 75% 61% Location: Federal Project: 04-SCL-130-5.6/6.0 ACST-PP13-0(4) Progress payment No. 004 Payment period ending: 08-20-17 BRIDGEWAY CIVIL CONSTRUCTORS INC 4950 ALLISON PKWY #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 669,877.49 84,776.80 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 669,877.49 84,776.80 5. Mobilization 100,000.00 0.00 6. Total Work Completed 769,877.49 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 769,877.49 84,776.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,776.80