Dept. of Trans. PROGRESS Serial No. Contract No. 19-140-11-06 04-2J0004 PROGRESS PAYMENT VOUCHER %complete: %time: 25% 19% Location: Federal Project: 04-CC-4-R16.4/R17.4 SNHG-P004(154) 04-CC-4-R19.5/R20.7 Progress payment No. 002 Payment period ending: 05-20-19 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 628,151.00 608,951.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 6,005.00 6,005.00 4. Earned Subject to Retention 634,156.00 614,956.00 5. Mobilization 262,500.00 262,500.00 6. Total Work Completed 890,651.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 896,656.00 877,456.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 877,456.00