Dept. of Trans. PROGRESS Serial No. Contract No. 20-055-14-02 04-2J0004 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 100% Location: Federal Project: 04-CC-4-R16.4/R17.4 SNHG-P004(154) 04-CC-4-R19.5/R20.7 Progress payment No. 011 Payment period ending: 02-20-20 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,065,522.85 6,300.00 2. a. Extra Work 256,332.20 18,466.53 b. Adustment Comp. -12,275.00 -7,540.00 3. Materials on Hand 4. Earned Subject to Retention 3,309,580.05 17,226.53 5. Mobilization 350,000.00 0.00 6. Total Work Completed 3,659,580.05 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,654,580.05 12,226.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,226.53