Dept. of Trans. PROGRESS Serial No. Contract No. 18-110-10-50 04-2J0304 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 16% Location: Federal Project: 04-CC-4-23.6/25.2 NONE Progress payment No. 003 Payment period ending: 04-20-18 EMPIRE LANDSCAPING INC 979 F ST #A DAVIS CA 95616 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,608.00 141,998.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 156,608.00 141,998.00 5. Mobilization 67,500.00 67,500.00 6. Total Work Completed 224,108.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 224,108.00 209,498.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 209,498.00