Dept. of Trans. PROGRESS Serial No. Contract No. 18-166-12-59 04-2J0304 PROGRESS PAYMENT VOUCHER %complete: %time: 45% 34% Location: Federal Project: 04-CC-4-23.6/25.2 NONE Progress payment No. 005 Payment period ending: 06-20-18 EMPIRE LANDSCAPING INC PO BOX 35 DAVIS CA 95617-0035 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 401,579.00 198,283.00 2. a. Extra Work b. Adustment Comp. 3,000.00 3,000.00 3. Materials on Hand 4. Earned Subject to Retention 404,579.00 201,283.00 5. Mobilization 85,500.00 0.00 6. Total Work Completed 490,079.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 490,079.00 201,283.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 201,283.00