Dept. of Trans. PROGRESS Serial No. Contract No. 19-294-10-12 04-2J0424 PROGRESS PAYMENT VOUCHER %complete: %time: 63% 95% Location: Federal Project: 04-CC-4-R28.7/R31.0 NONE Progress payment No. 007 Payment period ending: 10-20-19 J J NGUYEN INC 3172 SALEM DR SAN JOSE CA 95127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 534,772.50 184,086.00 2. a. Extra Work 328,057.11 0.00 b. Adustment Comp. -4,500.00 -4,500.00 3. Materials on Hand 4. Earned Subject to Retention 858,329.61 179,586.00 5. Mobilization 160,000.00 8,000.00 6. Total Work Completed 1,018,329.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,018,329.61 187,586.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 187,586.00