Dept. of Trans. PROGRESS Serial No. Contract No. 21-200-17-40 04-2J0424 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 04-CC-4-R28.7/R31.0 NONE Progress payment No. 028 Payment period ending: 07-20-21 J J NGUYEN INC 530 STOCKTON AVE SAN JOSE CA 95126 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 854,548.50 3,510.00 2. a. Extra Work 494,294.58 83,223.15 b. Adustment Comp. -6,500.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,342,343.08 86,733.15 5. Mobilization 160,000.00 0.00 6. Total Work Completed 1,502,343.08 7. Deductions -15,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,487,343.08 86,733.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 86,733.15