Dept. of Trans. PROGRESS Serial No. Contract No. 16-172-08-58 04-2J0804 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 43% Location: Federal Project: 04-SM-280-R2.1/10.8 NHPI-2801 1-144(E) Progress payment No. 002 Payment period ending: 06-20-16 GRANITE ROCK COMPANY 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,144,617.05 405,250.05 2. a. Extra Work 113,541.00 113,541.00 b. Adustment Comp. 3. Materials on Hand 0.00 -57,996.89 4. Earned Subject to Retention 2,258,158.05 460,794.16 5. Mobilization 772,875.00 0.00 6. Total Work Completed 3,031,033.05 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,031,033.05 460,794.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 460,794.16