Dept. of Trans. PROGRESS Serial No. Contract No. 17-206-10-37 04-2J1404 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 89% Location: Federal Project: 04-ALA-13 NHP-X001(599) 04-ALA-24 04-ALA-80 Progress payment No. 014 Payment period ending: 07-20-17 BC TRAFFIC SPECIALIST 638 W SOUTHERN AVE ORANGE CA 92865 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,086,901.27 306,336.77 2. a. Extra Work 205,615.00 205,615.00 b. Adustment Comp. -23,409.12 -23,409.12 3. Materials on Hand 4. Earned Subject to Retention 3,269,107.15 488,542.65 5. Mobilization 70,000.00 0.00 6. Total Work Completed 3,339,107.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,339,107.15 488,542.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 488,542.65