Dept. of Trans. PROGRESS Serial No. Contract No. 17-110-08-49 04-2J1504 PROGRESS PAYMENT VOUCHER %complete: %time: 5% 68% Location: Federal Project: 04-CC-4 NHP-X013(29) 04-CC-80 04-CC-580 Progress payment No. 002 Payment period ending: 04-20-17 CORAL CONSTRUCTION COMPANY PO BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 52,798.54 0.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 293,479.90 293,479.90 4. Earned Subject to Retention 346,278.44 293,479.90 5. Mobilization 72,000.00 72,000.00 6. Total Work Completed 124,798.54 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 418,278.44 365,479.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 365,479.90