Dept. of Trans. PROGRESS Serial No. Contract No. 16-139-14-13 04-2J1604 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 55% Location: Federal Project: 04-SOL-80 NHP-X095(28) 04-SOL-780 04-SOL-113 Progress payment No. 003 Payment period ending: 05-20-16 PETERSON - CHASE GENERAL ENGINEERING CONSTRUCTION, INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 528,018.00 46,869.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -21,458.00 4. Earned Subject to Retention 528,018.00 25,411.00 5. Mobilization 50,000.00 0.00 6. Total Work Completed 578,018.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 578,018.00 25,411.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 25,411.00