Dept. of Trans. PROGRESS Serial No. Contract No. 16-323-14-08 04-2J1804 PROGRESS PAYMENT VOUCHER %complete: %time: 34% 49% Location: Federal Project: 04-MRN-101 NHP-000C(415) 04-SON-101 04-NAP-29 Progress payment No. 001 Payment period ending: 11-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614-5706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 414,673.51 414,673.51 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 414,673.51 414,673.51 5. Mobilization 91,200.00 91,200.00 6. Total Work Completed 505,873.51 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 505,873.51 505,873.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 505,873.51