Dept. of Trans. PROGRESS Serial No. Contract No. 18-330-10-37 04-2J4804 PROGRESS PAYMENT VOUCHER %complete: %time: 22% 15% Location: Federal Project: 04-MRN-101 ACNH-Q101(324) 04-MRN-580 Progress payment No. 001 Payment period ending: 11-20-18 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 258,839.07 258,839.07 2. a. Extra Work 5,272.20 5,272.20 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 264,111.27 264,111.27 5. Mobilization 129,750.00 129,750.00 6. Total Work Completed 393,861.27 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 393,861.27 393,861.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 393,861.27