Dept. of Trans. PROGRESS Serial No. Contract No. 19-294-13-07 04-2J5604 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 15% Location: Federal Project: 04-MRN-1-0.3/0.3 NONE Progress payment No. 006 Payment period ending: 10-20-19 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 583,486.80 0.00 2. a. Extra Work 26,410.22 16,629.21 b. Adustment Comp. 2,608.97 2,608.97 3. Materials on Hand 4. Earned Subject to Retention 612,505.99 19,238.18 5. Mobilization 63,000.00 0.00 6. Total Work Completed 675,505.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 675,505.99 19,238.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,238.18