Dept. of Trans. PROGRESS Serial No. Contract No. 21-140-14-24 04-2J5704 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 100% Location: Federal Project: 04-NAP-121-20.6/20.6 NONE Progress payment No. 022 Payment period ending: 05-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 572,386.10 0.00 2. a. Extra Work 154,803.75 6,616.00 b. Adustment Comp. 27,343.93 0.00 3. Materials on Hand 4. Earned Subject to Retention 754,533.78 6,616.00 5. Mobilization 6. Total Work Completed 754,533.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 754,533.78 6,616.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,616.00