Dept. of Trans. PROGRESS Serial No. Contract No. 19-323-08-07 04-2J6704 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 93% Location: Federal Project: 04-ALA-238-R14.5/16.7 SIMG-238-1(6) Progress payment No. 011 Payment period ending: 11-20-19 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,484,586.90 81,000.00 2. a. Extra Work 221,639.18 33,013.09 b. Adustment Comp. 101,510.87 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,807,736.95 114,013.09 5. Mobilization 420,000.00 0.00 6. Total Work Completed 4,227,736.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,227,736.95 114,013.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,013.09