Dept. of Trans. FINAL Serial No. Contract No. 16-061-10-26 04-2J7104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SM-35-0.0/21.0 NONE 04-SCL-35-0.0/2.1 Progress payment No. 006 Payment period ending: 11-30-15 NORTHWEST PAVING 8115 SECLUDED VALLEY DR REDDING CA 96001 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,345,288.21 0.00 2. a. Extra Work 216,246.55 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,561,534.76 0.00 5. Mobilization 6. Total Work Completed 1,561,534.76 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,561,534.76 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00