Dept. of Trans. PROGRESS Serial No. Contract No. 24-165-11-34 04-2J7304 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 73% Location: Federal Project: 04-SM-101-6.9/7.6 ACNH-Q101(415) Progress payment No. 013 Payment period ending: 06-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,727,679.80 310,585.80 2. a. Extra Work 3,541,329.00 0.00 b. Adustment Comp. 2,065,120.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 19,334,128.80 310,585.80 5. Mobilization 1,320,000.00 0.00 6. Total Work Completed 20,654,128.80 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,654,128.80 310,585.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 310,585.80