Dept. of Trans. PROGRESS Serial No. Contract No. 20-237-09-04 04-2J7504 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 94% Location: Federal Project: 04-SCL-280-R2.9/R17.8 NONE Progress payment No. 008 Payment period ending: 08-20-20 DISNEY CONSTRUCTION INC 533 AIRPORT BLVD #120 BURLINGAME CA 94010 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,355,210.00 124,747.00 2. a. Extra Work 61,672.69 7,098.47 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,416,882.69 131,845.47 5. Mobilization 149,835.00 0.00 6. Total Work Completed 1,566,717.69 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,556,717.69 121,845.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 121,845.47