Dept. of Trans. PROGRESS Serial No. Contract No. 22-293-14-25 04-2J8024 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 37% Location: Federal Project: 04-SF-80-3.8/5.0 ACIM-801(120) Progress payment No. 015 Payment period ending: 10-20-22 F D THOMAS INC PO BOX 4663 MEDFORD OR 97501 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,477,976.72 819,819.14 2. a. Extra Work 24,828.00 0.00 b. Adustment Comp. 3. Materials on Hand 157,236.19 16,344.14 4. Earned Subject to Retention 8,660,040.91 836,163.28 5. Mobilization 2,185,000.00 0.00 6. Total Work Completed 10,687,804.72 7. Deductions -229,152.06 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,615,888.85 836,163.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 836,163.28