Dept. of Trans. PROGRESS Serial No. Contract No. 23-229-15-48 04-2J8024 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 64% Location: Federal Project: 04-SF-80-3.8/5.0 ACIM-801(120) Progress payment No. 025 Payment period ending: 08-20-23 F D THOMAS INC PO BOX 4663 MEDFORD OR 97501 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,443,234.72 473,031.86 2. a. Extra Work 51,014.16 0.00 b. Adustment Comp. 3. Materials on Hand 232,817.44 0.00 4. Earned Subject to Retention 16,727,066.32 473,031.86 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 18,794,248.88 7. Deductions -241,212.70 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,785,853.62 473,031.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 473,031.86