Dept. of Trans. PROGRESS Serial No. Contract No. 23-293-15-16 04-2J9504 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 36% Location: Federal Project: 04-SCL-9 HSST-X085(65) Progress payment No. 003 Payment period ending: 10-20-23 PTM GENERAL ENGINEERING SERVICES INC PO BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 497,390.52 222,211.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 109,774.43 0.00 4. Earned Subject to Retention 607,164.95 222,211.40 5. Mobilization 360,000.00 120,000.00 6. Total Work Completed 857,390.52 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 967,164.95 342,211.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 342,211.40