Dept. of Trans. PROGRESS Serial No. Contract No. 16-266-15-35 04-2K2304 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 17% Location: Federal Project: 04-SON-101-0.7/2.6 NONE Progress payment No. 001 Payment period ending: 09-20-16 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 24,077.84 24,077.84 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 24,077.84 24,077.84 5. Mobilization 6. Total Work Completed 24,077.84 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,077.84 24,077.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,077.84