Dept. of Trans. PROGRESS Serial No. Contract No. 23-044-11-21 04-2K2404 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 65% Location: Federal Project: 04-MRN-101-15.6/15.6 NONE 04-SON-101-16.5/16.5 04-SON-101-19.0/19.0 Progress payment No. 007 Payment period ending: 02-20-23 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 B VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,012,868.10 574,492.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -58,151.00 4. Earned Subject to Retention 2,012,868.10 516,341.00 5. Mobilization 330,000.00 16,500.00 6. Total Work Completed 2,342,868.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,342,868.10 532,841.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 532,841.00