Dept. of Trans. PROGRESS Serial No. Contract No. 24-290-10-35 04-2K6404 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 54% Location: Federal Project: 04-SM-84-6.0/6.0 ACST-P084(58) Progress payment No. 008 Payment period ending: 10-20-24 BRIDGEWAY CIVIL CONSTRUCTORS INC 3333 VACA VALLEY PKWY #2000 B VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,743,035.92 76,603.04 2. a. Extra Work 16,582.00 6,212.77 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,759,617.92 82,815.81 5. Mobilization 210,000.00 0.00 6. Total Work Completed 1,969,617.92 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,969,617.92 82,815.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 82,815.81