Dept. of Trans. PROGRESS Serial No. Contract No. 22-354-12-05 04-2K8104 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 9% Location: Federal Project: 04-VAR-80-17.2/19.2 ACST-X095(35) Progress payment No. 001 Payment period ending: 12-20-22 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 201,051.00 201,051.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 359,251.40 359,251.40 4. Earned Subject to Retention 560,302.40 560,302.40 5. Mobilization 277,500.00 277,500.00 6. Total Work Completed 478,551.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 837,802.40 837,802.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 837,802.40