Dept. of Trans. PROGRESS Serial No. Contract No. 23-080-10-36 04-2K8104 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 51% Location: Federal Project: 04-VAR-80-17.2/19.2 ACST-X095(35) Progress payment No. 004 Payment period ending: 03-20-23 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,351,822.00 356,211.00 2. a. Extra Work 25,562.58 20,188.18 b. Adustment Comp. 3. Materials on Hand 501,939.00 -40,272.27 4. Earned Subject to Retention 1,879,323.58 336,126.91 5. Mobilization 370,000.00 18,500.00 6. Total Work Completed 1,747,384.58 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,249,323.58 354,626.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 354,626.91